Bug #2075
closed
MF-->Schedule 4-->Qus.no 22 (B) -->When the applicant selects the date field and selects add row then sequence is getting wrong
Added by Mohd Irfan over 2 years ago.
Updated over 2 years ago.
Description
Step to reproduce bug:
MF-->Schedule 4-->Qus.no 22 (B) -->When the applicant selects the date field and selects add row then the sequence is getting wrong
See attached screenshot:
Files
- Status changed from New to Resolved
- File clipboard-202204151550-htcej.png clipboard-202204151550-htcej.png added
- Subject changed from MF-->Schedule 4-->Qus.no 22(A) (B) -->When the applicant selects the date field and selects add row then sequence is getting wrong to MF-->Schedule 4-->Qus.no 22 (B) -->When the applicant selects the date field and selects add row then sequence is getting wrong
- Description updated (diff)
- Status changed from Resolved to Reopened
This issue has been verified.
and it has been found that the issue is not fixed.
- Status changed from Reopened to Resolved
- Status changed from Resolved to Closed
This issue has been verified.
and it has been found that the issue is fixed.
Also available in: Atom
PDF